Approving Individual Lines
The Hours tab and the Materials tab both let you work on single lines instead of the whole order.
Approving lines
- Select the lines with their checkboxes, or take the whole page with the checkbox in the heading row.
- Click Approve in the bar at the bottom of the tab.
- Confirm. For materials the question reads “Are you sure you want to approve 12 selected materials? Items will be set to Final Approval, for financial control.”
Selecting everything does not select the lines that cannot be selected at all. On an order with fifteen material lines where two are already invoiced, the heading checkbox reports 13 of 15 row(s) selected.
Approve never refuses a whole selection
Lines that cannot be approved are skipped and the rest go through. So you do not have to pick your lines apart first — select the lot and read what will be skipped.
Why a material line is skipped
- Material already approved — Nothing left to do.
- Material is non-billable — The line is left out of invoicing. Mark it billable first.
- Material has zero quantity — Nothing was used, and picking is not complete.
- Planned material has not been picked yet — The planned quantity has not been reported as picked.
- Supplier is restricted for this user — The material comes from a supplier outside your trade group, or has no supplier recorded.
Why an hour line is skipped
- Time entry is already approved — Nothing left to do.
- Time entry is non-billable — Left out of invoicing.
- Time entry has zero hours — No hours registered. Hours have no picking rule, so zero is never approvable.
- Time entry’s salary code is not to be invoiced — Only while the invoice basis preview is open. The code is never billable.
There is no restriction on approving hours that you registered yourself.
Two states are missing from those lists on purpose
A line that is already invoiced, and a line booked to an invoice draft other than the one you have open, cannot be selected at all. Their checkboxes are unavailable, so Approve never has to skip them.
They matter for the other actions instead: those are the lines that refuse an Unapprove, a Non-billable or a Mark as billable.
When part of your selection cannot be approved
A window opens before anything happens. It says how many lines are affected — 15 of 25 items will be affected. 10 will be skipped. — then lists Will be applied (15) and Will be skipped (10) as two groups, with a reason on every skipped row. The button reads Apply to 15 items.
Taking a line approval back
Select lines that are already approved and Approve changes to Unapprove. Every line in your selection has to be approved for that swap to happen.
Unlike approving, Unapprove does refuse: if any line in your selection is already invoiced, the whole selection is refused rather than skipped.
Approving lines is not the same as approving the order
The order keeps its own approval status. Working through the lines does not move the order to Approved. That needs Approve order inside the order, or Approve from the order list.